The
Program anticipates a funding level of up to $50,000 for the contract
awards resulting from this BIA.
Detailed
Description of Effort and Task
The
Mission Execution and Battle Management subsystem is one of five C2
subsystems that are common components for all manned ground vehicles.
It provides the mission execution and battle management software for
FCS.
All components
will be based on open system architecture to facilitate block upgrades
and spiral development throughout the life of the C2 system.
The supplier
shall assist the LSI in understanding, developing, and documenting
the Mission Execution and Battle Management subsystem requirements
and architecture and writing the Mission Execution and Battle Management
subsystem specification.
Task
1
Analyze
FCS C2 requirements for Mission Execution and Battle Management Subsystem
requirements and architecture.
Task
2
Assist
LSI in writing the Mission Execution and Battle Management Subsystem
architecture and design description, interface architecture description,
specification, and ROM cost models. The LSI will provide a preliminary
version of these documents and specification for completion by the
supplier.
Task
3
Demonstrate
your ability to meet a PDR within 30 days of SDD authorization (currently
set for 7/03) should you be chosen as an SDD supplier.
Schedule
and duration of on-site support - None
Number,
duration(s) and location(s) of meetings
3
Technical Interchange Meetings (TIM) at Seattle, WA - First TIM 2
days, second and third TIM ½ day
Schedule
Milestones
Subcontract
Start Date - 10/9/02
Subcontract
Completion Date - 12/16/02
Initial
Coordination Meeting - 10/10/02-10/11/02 (Seattle, WA)
Interim
Coordination Meeting - Week of 10/28/02 (Seattle, WA)
Final
Coordination Meeting - Week of 11/18/02 (Seattle, WA)
Data
Requirements - None
Deliverables:
C2 Mission
Execution and Battle Management Subsystem Architecture & Design Description
document. Initial Draft 10/25/02; Final Draft 11/15/02.
C2 Mission
Execution and Battle Management Subsystem Interface Architecture document.
Initial Draft 10/25/02; Final Draft 11/15/02.
C2 Mission
Execution and Battle Management Subsystem Specification. Initial Draft
10/25/02; Final Draft 11/15/02.
C2 Mission
Execution and Battle Management Subsystem ROM cost models document.
Initial Draft 10/25/02; Final Draft 11/15/02.
Evaluation
Criteria
Offerors
should ensure that their proposals address the following:
- Demonstrated
credibility of the proposed technical approach
- Degree
of understanding of the technical aspects of the work and related
issues
- Relevance
and history of performing similar work
- Availability
of resources to successfully conduct the proposed work.
- Responsiveness
to general BIA instructions
We will
apply these considerations in the following areas:
- Experience
in the role of a subsystem integrator
- Suitability
to perform as a future C2 Mission Execution & Battle Management
developer and integrator
- Demonstrated
ability to meet early PDR