Number: 16200.5
Pricing
Information
The
Program anticipates a funding level of up to $50,000 for the contract
awards resulting from this BIA.
Detailed
Description of Effort and Task
The
Situation Understanding subsystem is one of five C2 subsystems that
are common components for all manned ground vehicles. It provides
the situation understanding application software for FCS.
All components
will be based on an open system architecture to facilitate block upgrades
and spiral development throughout the life of the C2 system.
The supplier
shall assist the LSI in understanding, developing and documenting
the Situation Understanding subsystem requirements and architecture
and writing the Situation Understanding subsystem specification.
Task
1
Analyze
FCS C2 requirements for Situation Understanding Subsystem requirements
and architecture.
Task
2
Assist
LSI in writing the Situation Understanding Subsystem architecture
and design description, interface architecture description, specification,
and ROM cost models. The LSI will provide a preliminary version of
these documents and specification for completion by the supplier.
Task
3
Demonstrate
your ability to meet a PDR within 30 days of SDD authorization (currently
set for 7/03) should you be chosen as an SDD supplier.
Schedule
and duration of on-site support - None
Number,
duration(s) and location(s) of meetings
3
Technical Interchange Meetings (TIM) at Seattle, WA - First TIM 2
days, second and third TIM ½ day
Schedule
Milestones
Subcontract
Start Date - 10/9/02
Subcontract
Completion Date - 12/16/02
Initial
Coordination Meeting - 10/10/02-10/11/02 (Seattle, WA)
Interim
Coordination Meeting - Week of 10/28/02 (Seattle, WA)
Final
Coordination Meeting - Week of 11/18/02 (Seattle, WA)
Data
Requirements - None
Deliverables
C2 Situation
Understanding Subsystem Architecture & Design Description document.
Initial Draft 10/25/02; Final Draft 11/15/02.
C2 Situation
Understanding Subsystems Interfaces Architecture document. Initial
Draft 10/25/02; Final Draft 11/15/02.
C2 Situation
Understanding Subsystem Specification. Initial Draft 10/25/02; Final
Draft 11/15/02.
C2 Situation
Understanding Subsystem ROM cost models document. Initial Draft 10/25/02;
Final Draft 11/15/02.
Evaluation
Criteria
Offerors
should ensure that their proposals address the following:
- Demonstrated
credibility of the proposed technical approach
- Degree
of understanding of the technical aspects of the work and related
issues
- Relevance
and history of performing similar work
- Availability
of resources to successfully conduct the proposed work.
- Responsiveness
to general BIA instructions
We will
apply these considerations in the following areas:
- Experience
in the role of a subsystem integrator
- Suitability
to perform as a future C2 Situation Understanding developer and
integrator
- Demonstrated
ability to meet early PDR