Modifications to the first
737 Airborne Early Warning and Control (AEW&C) platform for
Australia’s Project Wedgetail are moving ahead on schedule.
With
great fanfare, and the Australian Minister of Defence looking
on, the green 737-700 was rolled out of the Boeing factory in
Renton, Wash. last October. Around the first of the year, it was
flown to Delaware where an auxiliary fuel system and four tanks
were installed and FAA certified. Those tanks were later removed
and will be stored until flight testing of the aircraft is completed
in 2004.
The plane was flown back to Puget Sound at the end of March for
major structural modifications where the transformation to an
AEW&C platform is underway inside a huge hangar at Boeing
Field in Seattle.
“The work has gone extremely well”, said Patrick
Gill, Boeing vice president of 737 AEW&C programs.
“With our digital design, the parts go together the right
way, the first time around,” Gill said. “For example,
pilot holes drilled from two different manufacturers in two different
locations fit perfectly.”
“Not only are we on schedule and within our target man-hours,
but the quality of the design, parts fabrication and the installation
work is excellent.”
It’s no accident that Puget Sound is handling the modification
job. Boeing looked at all locations throughout the U.S. —
balancing risk, shipside engineering support, customer involvement,
cost and schedule – and Puget Sound came out on top, said
Rich Lukezic, Boeing senior manager for aircraft modification
on the 737 AEW&C program.
“First
off, this is the home of the 737. The workforce is available,
knowledgeable and experienced,” he said.
Puget Sound workers have experience building the 767 AWACS planes,
which are similar to the 737 AEW&C program and can build on
lessons learned from that program.
“When you’re talking about a developmental program
of a limited quantity, there is a real advantage to keeping manufacturing
resources close to engineering and working as one team. Here we
can keep a short line of communication so changes to the plan
have a minimal impact,” Lukezic said.
The program is committed to utilizing new processes and approaches
and to maximize the use of the digital design model straight to
the shop floor.
“We made sure we’re giving the mechanics the same
tools the engineers are using,” he said.
While modifications are underway, design reviews have been completed
on radar /identification friend or foe, mission computing, mission
navigation and communications subsystems and the airborne mission
system. Additionally, BAE SYSTEMS Australia, under subcontract
to Boeing, has completed four major design reviews covering electronic
warfare self-protection and electronic support measures along
with the mission support segment and operational mission simulator.
These reviews have been completed on schedule and on budget.
Software development for the Wedgetail program also is progressing.
Using a strategy of building each new functionality incrementally
and integrating and testing along the way, Boeing is validating
the architecture and performance – catching and fixing problems
early while mitigating key risk areas. The first production software
build was completed last spring with the next build scheduled
to be completed in the fall.
Gill
says working together is key to the Wedgetail program successfully
pushing forward.
“We have outstanding teamwork among our customer, suppliers
and Boeing and between engineering and operations,” he said.
“You can feel the enthusiasm, excitement, commitment and
shared values from people working on Wedgetail. There’s
a real sense of accomplishment.”
The Australian Defence Force selected the 737 AEW&C system
in July 1999. A contract was signed in December 2000 for four
AEW&C systems plus options for three additional systems. The
first two 737 AEW&C aircraft are scheduled to be delivered
to Australia in 2006.
In November 2000, the Republic of Turkey selected a Boeing-led
team to begin contract negotiations on developing a new AEW&C
system. A contract was signed in June 2002 and officially started
in July 2003. The acquisition includes four 737 AEW&C aircraft
plus ground support segments for mission crew training, mission
support and system maintenance support. Delivery of Turkey's first
737 AEW&C system is scheduled for 2007.
|