Back
to main article
A hangar project team
should consider the following points during the planning process:
- Rarely
will a project be completed without spending at least 5 percent
of the construction bid price on errors, omissions, and unforeseen
conditions. A 10 percent construction cost contingency is recommended
for normal projects, and even greater contingencies are recommended
for highly complex, incompletely scoped, or fast-track projects.
Construction contingency should not be used to fund optional changes
that are not related to errors or unforeseen conditions.
- Errors, omissions,
and unforeseen conditions can be minimized by having an experienced
construction professional (versus a design professional) review
the planning and design drawings. This should save 3 percent of
construction cost by minimizing design-related flaws.
- The hangar project
team should avoid using other hangar drawings as a starting point
for its own. The best way to plan and design a hangar is to start
from scratch. If the hangar project team uses someone else’s drawings
as a starting point, the team will build a hangar that meets someone
else’s needs — not its own.
- When planning a hangar
facility, the team must envision airline needs for the next 20
years and then site the hangar accordingly. For example, if the
airline needs a second hangar in five years, operations will be
much more efficient if the second hangar can be placed adjacent
to the one presently in planning. In this case, the team should
plan to have the additional space available for expansion should
the need arise.
- The team also needs
to establish early on what the airport will provide at its expense
and what the airline will be required to provide. For example,
some airports will pay for the ramp construction in front of the
new hangar; others will not.
- There is no single
best way to contract a hangar project. The selected contract path
should be tailored to the needs of the specific project. (If the
project is poorly managed or the contractor is inexperienced or
untrustworthy, no contract is strong enough to offset the potential
high costs and schedule delays.)
- A successful project
carefully balances schedule, cost, and quality, placing appropriate
emphasis on each factor. Very inexpensive projects may cost an
airline more money in the long run because of operational inefficiencies
and high maintenance charges. Fast-track projects will certainly
cost more than projects completed under normal schedules. High-technology,
high-quality hangars will cost more than basic facilities.
- Airplane hangars often
are too small as soon as they are built. As airlines change strategies
and new airplanes come to market, hangar size requirements change
accordingly. A rule of thumb is to size a new hangar for the next
larger airplane than currently anticipated. For example, a Boeing
737-700 airline should consider sizing its new hangar to fit a
757-200.
- Regardless of pressures
to tighten the project schedule, the hangar project team must
not lose sight of the value of good planning. Because progress
often is measured by tangible factors such as the quantity of
completed design drawings or by the amount of construction work
in place, planning sometimes will be viewed by others as lack
of progress. This perception is accentuated when project schedules
are tight.
- Studies of the best
aviation companies have shown that good project planning is even
more important in a fast-track environment. In a fast-track environment,
an effective project team establishes a strong project plan and
then accelerates design and construction to meet the scheduling
goals of the project. One of the worst mistakes a hangar project
team can make is to sacrifice planning to accelerate the project
schedule.
|